Pond Update Information
Posted on May 28th, 2019
Here is a rough timeline for the items on the pond at Burberry. (This is from our pond contractor)
Aeration system is at our shop and I’m working to get it on schedule for late next week or Thursday the following depending on weather. I will install the turtle trap at the same time and pull the existing fountain for repairs.
Fish orders have been placed and will be delivered within 2-3 weeks. Once we are given a firm date by our supplier we will let you know.
Sam said he would be getting started on the erosion control within 40 days, should be sooner but he didn’t want to over promise based on the weather we have been experiencing.